A heuristic for multi-period disassembly leveling and scheduling

Dong Hyun Kim, Dong Ho Lee

Research output: Chapter in Book/Report/Conference proceedingConference contributionpeer-review

8 Scopus citations

Abstract

We consider disassembly leveling and scheduling for multiple product types with parts commonality. Disassembly leveling, one of disassembly process planning decisions, is to determine disassembly structures that specify parts and subassemblies to be obtained from used/end-of-life products, and disassembly scheduling is the problem of determining the timing and quantity of disassembling products and their subassemblies to satisfy the demands of their parts and/or subassemblies. Unlike the previous studies, we consider the two problems at the same time, especially in multi-period version for the objective of minimizing the sum of disassembly setup, disassembly operation and inventory holding costs. In particular, we consider the general case that disassembly levels may be different for products of the same type and different periods. To represent the integrated problem mathematically, an integer programming model is developed. Then, as an initial solution approach, a simple greedy heuristic using a priority rule is suggested and its performance is reported.

Original languageEnglish
Title of host publication2011 IEEE/SICE International Symposium on System Integration, SII 2011
Pages762-767
Number of pages6
DOIs
StatePublished - 2011 Dec 1
Event2011 IEEE/SICE International Symposium on System Integration, SII 2011 - Kyoto, Japan
Duration: 2011 Dec 202011 Dec 22

Publication series

Name2011 IEEE/SICE International Symposium on System Integration, SII 2011

Other

Other2011 IEEE/SICE International Symposium on System Integration, SII 2011
CountryJapan
CityKyoto
Period11/12/2011/12/22

Fingerprint Dive into the research topics of 'A heuristic for multi-period disassembly leveling and scheduling'. Together they form a unique fingerprint.

Cite this